| Phase |
Component |
Construction |
Commissioning |
Progress |
| 1 |
Raising of Flag Boshielo Dam |
2004 – 2006 |
2006 |
Completed |
| 2A |
De Hoop Dam |
2006 – 2010 |
2009 |
In Progress |
| 2B |
Flag Boshielo to Mokopane pipeline |
2008 – 2009 |
2009 |
To be started |
| 2C |
Steelpoort Weir and abstraction works |
2008 – 2009 |
2009 |
|
| 2D |
2nd pipeline from Steelpoort Weir to Mooihoek |
2010 – 2011 |
2011 |
|
| 2E |
2nd pipeline parallel to Lebalelo Scheme |
> 2025 |
|
|
| 2F |
Connect Lebalelo Scheme to Olifantspoort |
2012 – 2013 |
2013 |
|
| 2G |
2nd pipeline from Flag Boshielo to Mokopane |
> 2025 |
|
|
| 2H |
Incorporate Lebalelo Scheme |
2008 – 2009 |
2009 |
|