|
Vanderkloof Dam (previously the PK le Roux Dam) is situated 130km downstream of Gariep dam on the Orange River. It forms the second largest storage
reservoir in South Africa with a capacity of over 3 200 million m3.
The dam forms an integral component of the Orange River
Project (together with Gariep Dam) and supplies water to the Riet River catchment as well as to the various users along the
remaining 1 400 km of the Orange River.

Click on image for full size photo
The Vanderkloof Dam is currently the highest dam in South Africa with a wall height of
107m and a crest length of 765m. Similar to Gariep Dam , it is a composite gravity arch
dam containing 1.1 million m3 of concrete and has a
central arch which transitions into a gravity flank on the left bank.

Click on image for full size photo
Vanderkloof Dam was originally scheduled to commence at the same time as the Gariep
Dam, but in October 1967, construction was postponed in accordance with government
measures to curb inflation in the national economy. During 1969, the Cabinet decided to
proceed with the project and in 1970 tenders were requested for a second time. The tender
prices received, were much higher than expected with the result that Cabinet decided that
the Department of Water Affairs should construct the dam using their own construction
staff and equipment.

Click on image for full size photo
The Vanderkloof Dam was designed by a consortium of local and overseas consultants and
constructed by the Department of Water Affairs and Forestry. Construction started in April
1971 and the dam was finally commissioned in September 1977.
Four gates installed in the wall can discharge up to 8 500 m3/s
in total through the flood sluices which are positioned on the left flank of the dam.
Water released from the Gariep Dam flows into Vanderkloof Dam where it is either
transferred through the Orange/Riet Canal to the Riet River
basin or released downstream through two hydro-power generators. The generators can each
produce 120 MW of electricity at a discharge of approximately 200 m3/s.
The hydro-power plant can therefore provide up to 240 MW of electricity at a flow rate of
400 m3/s.

It was originally envisaged that the right bank canal would extend to the Brak River
Valley in the Prieska-Britstown area as well as the Carnarvon-Leegte, the Beervlei area,
the Sak River Valley and the Koa River Valley. Due to economic factors concerning the
financial viability of the developments required, however, it was decided not to proceed
with the extensions of the right bank canal which now stops near Hopetown. Similarly, it
was originally intended to construct a left bank canal from the dam to Hopetown in order
to supply irrigation along the left bank of the Orange River. This canal was not
constructed and all irrigation along the left bank between Vanderkloof Dam and Hopetown is
supplied directly from the river using pumps.

Click on image for full size photo
|